Topping units are small refineries which will produce fuel to power gas turbine generators at the stations south of the Brooks Range., 1977-04
Item — Folder: PCA0002-4b
Identifier: PCA0002-4b-41
Scope and Contents
PS6055-19
Dates:
Issued: 1977-04
North of the Range, natural gas from Prudhoe will be used., 1977-04
Item — Folder: PCA0002-4b
Identifier: PCA0002-4b-42
Scope and Contents
PS6057-12
Dates:
Issued: 1977-04
Each pump station has three turbines, required for the 1.2 million barrel-per-day capacity of the pipeline. Two turbines will operate, and the third will be on standby., 1977-04
Item — Folder: PCA0002-4b
Identifier: PCA0002-4b-43
Scope and Contents
PS6060-13
Dates:
Issued: 1977-04
The 13,500 horsepower turbines are similar to those used in jet aircraft., 1977-04
Item — Folder: PCA0002-4b
Identifier: PCA0002-4b-44
Scope and Contents
PS6059-18
Dates:
Issued: 1977-04
Setting and alignment of all turbines is now complete., 1977-04
Item — Folder: PCA0002-4b
Identifier: PCA0002-4b-45
Scope and Contents
PS6060-18
Dates:
Issued: 1977-04
Final testing of the equipment is in progress, and all stations are preparing for start-up operations., 1977-04
Item — Folder: PCA0002-4b
Identifier: PCA0002-4b-46
Scope and Contents
PS3044-3
Dates:
Issued: 1977-04
Here, at the pump station 2 location, and at other stations not required for the 1.2 million barrel capacity of the pipeline, all remained quiet. These “pass through” stations, partially completed last fall, do not have facilities or pumping capabilities. They may be completed as working pump stations if at a future date the pipeline capacity is increased above the 1.2 million barrels per day., 1977-04
Item — Folder: PCA0002-4b
Identifier: PCA0002-4b-47
Scope and Contents
PS2063-15
Dates:
Issued: 1977-04
Work at the 1,000 acre Valdez tanker terminal remained steady throughout the first quarter of the year., 1977-04
Item — Folder: PCA0002-4b
Identifier: PCA0002-4b-48
Scope and Contents
VT6152-9
Dates:
Issued: 1977-04
By April, all five metering skids in the west metering building were installed. Instruments in this building still measure the amount of incoming crude oil., 1977-04
Item — Folder: PCA0002-4b
Identifier: PCA0002-4b-49
Scope and Contents
VT9068-7
Dates:
Issued: 1977-04
Facilities in the ballast water skimmer building were essentially complete. Oily ballast from tankers will be cleansed at this facility through a chemically aided, air floatation process., 1977-04
Item — Folder: PCA0002-4b
Identifier: PCA0002-4b-50
Scope and Contents
VT4052-3
Dates:
Issued: 1977-04