PS8: Here at pump station 8, the concrete pad for the pipe corridor was being laid., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-71
Scope and Contents
PS633-16
Dates:
Issued: 1976-05
PS2: Preparation for corridor work also began at the four stations, known as "pass through" stations, not required until the pipeline capacity is increased above the 1.2 million barrel initial daily operation capacity. This is station 2., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-72
Scope and Contents
PS233-4A
Dates:
Issued: 1976-05
PS1: This aerial view of pump station 1, shows the 100-foot-high oxidizer, which will receive and consume excess vapor from the crude oil tanks at the station., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-73
Scope and Contents
PS152-8
Dates:
Issued: 1976-05
Terminal: Construction activity remained high through the reporting period in every area of the Valdez terminal facility. Ringwalls were being constructed for the four crude storage tanks in the west tank farm, and work was in progress on tanks remaining to be completed in the east tank farm., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-74
Scope and Contents
VT668-11A
Dates:
Issued: 1976-05
Terminal: Work continued on the four berths being constructed for the initial operation of the pipeline., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-75
Scope and Contents
VT548-20
Dates:
Issued: 1976-05
Terminal: 12 of 13 trestle pier jackets had been set for berth 5. Work on the anchor pilings for berth 1 was in progress., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-76
Scope and Contents
VT555-3
Dates:
Issued: 1976-05
Terminal: Here on berth 4, drains, piping and electrical conduit were being installed., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-77
Scope and Contents
VT558-8
Dates:
Issued: 1976-05
Terminal: Concrete floor slabs and support steel were added to the facilities in the power generation and vapor recovery area. Equipment installation included setting the fourth compressor in the compressor building, and setting the second and third cold condensate pumps, the upper shell on the second turbine and installing generator covers in the generator area., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-78
Scope and Contents
VT665-17
Dates:
Issued: 1976-05
Other work at the terminal included installation of piping, erection of pipe supports and construction of containment walls in the ballast treatment area., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-79
Scope and Contents
VT666-16
Dates:
Issued: 1976-05
AS122: By early May, the workforce on the project neared the 20,000 mark, as work continued toward the completion goal of mid-1977., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-80
Scope and Contents
WI103-16
Dates:
Issued: 1976-05