Folder PCA0002-1b
Container
Contains 80 Results:
Salcha River: The floats facilitate the dragging of the line into the ditch. After the pipe is pulled across the river, the floats are removed., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-21
Scope and Contents
PC6171-9
Dates:
Issued: 1976-05
Chatinika River: Here, about 20 miles north of Fairbanks, the line is being pulled across the Chatinika River., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-22
Scope and Contents
PC6198-9
Dates:
Issued: 1976-05
Bonanza Creek: In the river floodplain area, outside the river channel, the pipe is not coated with concrete, but is sunk to the bottom by concrete weights set atop the pipe., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-23
Scope and Contents
PC6164-9
Dates:
Issued: 1976-05
AS 96: These "saddle weights" weigh about 9 tons each, 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-24
Scope and Contents
PC2220-9
Dates:
Issued: 1976-05
Delta River: By early May, more than 26 miles of pipeline had been installed at river crossings along the 800 mile route. The work here is on the delta river floodplain, about 215 miles north of Valdez., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-25
Scope and Contents
PC2211-3A
Dates:
Issued: 1976-05
AS99: More than 425 miles of pipeline were installed by early May. 230 miles of this total were buried line. Here the line is being taped and lowered into a ditch south of the Brooks Range., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-26
Scope and Contents
PC2212-16
Dates:
Issued: 1976-05
Fairbanks Area: An ongoing audit program of all completed mainline welds has been conducted since last fall. Audit results, in some cases, indicate the need to repair or replace a weld. In other cases, only a new radiograph is required., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-27
Scope and Contents
PC307-8
Dates:
Issued: 1976-05
AS42: Repair of welds was one of the activities under way during the reporting period. Here a "bell hole" has been excavated to enable crew to make a new radiograph--or x-ray--of the pipe weld., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-28
Scope and Contents
PC306-3
Dates:
Issued: 1976-05
AS27: A small section of the pipeline was installed at a "special burial" location, about 30 miles north of Glennallen., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-29
Scope and Contents
PC007-11
Dates:
Issued: 1976-05
AS27: About four miles of insulated pipe encased in a fibrous glass coating were buried in an ice-rich permafrost area, where normally the line would be elevated., 1976-05
Item — Folder: PCA0002-1b
Identifier: PCA0002-1b-30
Scope and Contents
PC012-5A
Dates:
Issued: 1976-05