Folder PCA0002-3a
Container
Contains 80 Results:
(71) Liner was being applied to the impound basin in the Ballast Water Treatment area, and equipment installation and hydrotesting of all tankage was completed., 1976-09
Item — Folder: PCA0002-3a
Identifier: PCA0002-3a-71
Scope and Contents
VT7050-8
Dates:
Issued: 1976-09
(72) Piping excavation, pipe installation and back-filling continued at a number of locations on the terminal site., 1976-09
Item — Folder: PCA0002-3a
Identifier: PCA0002-3a-72
Scope and Contents
VT9033-13
Dates:
Issued: 1976-09
(73) The exterior panel installation was completed on all but two sides of the scraper and metering building., 1976-09
Item — Folder: PCA0002-3a
Identifier: PCA0002-3a-73
Scope and Contents
VT9029-2
Dates:
Issued: 1976-09
(74) Equipment installation at the terminal facilities included setting the control panels in the power plant., 1976-09
Item — Folder: PCA0002-3a
Identifier: PCA0002-3a-74
Scope and Contents
VT6131-1
Dates:
Issued: 1976-09
(75) Loading arm bases were set and ballast and crude lines connected on Berth 4., 1976-09
Item — Folder: PCA0002-3a
Identifier: PCA0002-3a-75
Scope and Contents
VT5070-4
Dates:
Issued: 1976-09
(76) Drilling for the berthing dolphins was completed and dolphins set at Berth 5. Work continued on installation of Berth 3 casing piles and Berth 1 anchor piles., 1976-09
Item — Folder: PCA0002-3a
Identifier: PCA0002-3a-76
Scope and Contents
VT5064-12
Dates:
Issued: 1976-09
(77) In addition to pipe trenching and backfilling, other earthwork activities in the terminal area included stabilizing slopes along the roadways., 1976-09
Item — Folder: PCA0002-3a
Identifier: PCA0002-3a-77
Scope and Contents
VT2061-8
Dates:
Issued: 1976-09
(78) In this “shotcreting” operation, concrete is sprayed over a reinforcing wire mesh., 1976-09
Item — Folder: PCA0002-3a
Identifier: PCA0002-3a-78
Scope and Contents
VT2060-10
Dates:
Issued: 1976-09
(79) Work on the terminal, pump stations and pipeline progressed significantly during the summer months of 1976, as the project remains on schedule to be operational in mid-1977., 1976-09
Item — Folder: PCA0002-3a
Identifier: PCA0002-3a-79
Scope and Contents
EQ3013-13
Dates:
Issued: 1976-09
Alyeska Pipeline Service Company [View of caribou standing on hilltop. Final slide in report.], 1976-09
Item — Folder: PCA0002-3a
Identifier: PCA0002-3a-80
Scope and Contents
WI3042-4A
Dates:
Issued: 1976-09