The longest river crossing on the route is across the Yukon River. Pipe is scheduled to be installed on the pipeway off the side of the highway bridge during August., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-49
Scope and Contents
YB504-3
Dates:
Issued: 1976-07
Other pipeline “crossings” that took place included highway crossings., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-50
Scope and Contents
PC6285-8
Dates:
Issued: 1976-07
Here, a multiplate culvert is assembled for a crossing beneath “Goldstream Road”, just north of Fairbanks., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-51
Scope and Contents
PC6285-9
Dates:
Issued: 1976-07
The culvert is made of galvanized corrugated steel sections that are bolted together at the crossing., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-52
Scope and Contents
PC6285-15
Dates:
Issued: 1976-07
There are 56 similar road crossings along the route., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-53
Scope and Contents
PC6267-8
Dates:
Issued: 1976-07
In May, an aerial “dusting bombing” operation was used just north of Valdez to accelerate snow melting along the right of way into Keystone Canyon and Thompson Pass., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-54
Scope and Contents
AC126-6
Dates:
Issued: 1976-07
A modified B-26 aircraft flew about 70 missions out of Valdez dropping the coal dust., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-55
Scope and Contents
AC127-10
Dates:
Issued: 1976-07
About, 140 tons of coal dust was used in the operation., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-56
Scope and Contents
AC129-6
Dates:
Issued: 1976-07
The black dust, which readily absorbs the sun’s rays, hastened the melting of the snow and enabled construction work to get under way by early June., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-57
Scope and Contents
AC126-13
Dates:
Issued: 1976-07
Right of way work in the Canyon was expected to be completed in late July, with pipeline installation beginning at that time., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-58
Scope and Contents
PC7154-1A
Dates:
Issued: 1976-07