Skip to main content

Folder PCA0002-6

 Container

Contains 71 Results:

Suspended by cable above its craggy destination, a segment of four foot diameter pipe for the trans Alaska pipeline is lowered into a bedrock trench at Thompson Pass., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-41
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

Crews prepare the alignment of a segment of pipe at Thompson Pass. The operator of the cable system maneuvers the pipe into place by maintaining radio contact with workers at the ditch. A special concrete mixture will be used in this ditch to backfill the pipe., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-42
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

Members of a pipe gang “fly” to their work sites aboard the cable system at Thompson Pass. The huge clamps, dangling in mid-air, normally are tightly wrapped around 80-foot long sections of mainline pipe., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-43
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

Pipeline welders complete the “tie-in” the final weld, for the Thompson Pass section of the trans Alaska pipeline project. One of the most difficult stretches of terrain on the 800-mile pipeline, Thompson Pass,, at 2500 feet, is the third highest elevation along the pipeline’s route., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-44
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

Workers fight snow, cold and mountainous terrain to align two sections of 48-inch diameter pipe on the steep slopes at Thompson Pass on the trans Alaska pipeline project., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-45
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

Snow-covered mountains of the Chugach Rangte loom in the background of Thompson Pass, where a cable tram was set up to haul materials and pipe up the 2,500-foot slope. At places, the pipeline rises at a 45-degree angle at Thompson Pass, near the southernmost section of the 800-mile trans Alaska pipeline., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-46
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

A section of 48-inch pipe, pre-bent and pre-coated, awaits backfilling near Thompson Pass, about 20 miles northeast of Valdez. Blowing snow which filled the ditch had to be removed before the backfilling could begin. On extreme grades, a special concrete mixture was used to backfill the pipe., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-47
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

Night or day, work on the 3,700-foot long Thompson Pass section of the trans Alaska pipeline was slow and difficult. Night shift crews used powerful portable generators, airlifted to the site, to illuminate the work area., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-48
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

One of the most difficult construction segments on the trans Alaska pipeline project is at Atigun Pass in the Brooks Mountain Range. In the foreground a trio of sideboom tractors lowers in a section of 48-inch diameter pipe at the north end of the pass., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-49
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

A cage of fabricated metal tubing protects workers as they spread concrete grout in a special pipe ditch section at Atigun Pass on the trans Alaska pipeline project. The cages were constructed because crews working the ditch otherwise would be vulnerable to falling rocks from the steep slopes in the area., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-50
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977