Skip to main content

Folder PCA0002-6

 Container

Contains 71 Results:

An above ground section of the trans Alaska pipeline zigzags north across the flat, snow swept plains of the North slope, about 50 miles south of Prudhoe Bay. The sigzag configuration of the pipeline will convert thermal expansion of the steel pipe into a sideways movement of the pipeline., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-1
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

Three cranes are used to lift a boiler stack – the length of a football field – into position at the Valdez terminal of the Trans Alaska pipeline. The stack, weighting 408 tons, is 21-1/2 feet in diameter at the base., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-2
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

Crossbars and cradles were added to this bulldozer so it could carry two 80-foot sections of the 48-inch diameter pipe up the steep, narrow work roads in Keystone Canyon. The canyon, about 18 miles east of Valdez, is one of the most challenging sections along the 800-mile route of the trans Alaska pipeline., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-3
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

A 300-foot-high boiler stack towers above other facilities at the Valdez terminal of the trans Alaska pipeline. The stack is part of the terminal’s power plant., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-4
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

An 80-foot-long section of 4-foot-diameter pipe is loaded onto a bulldozer, which has been modified to carry two sections of pipe. The blade and ripper were removed from the dozer and the cradles added so the vehicle could carry the pipe up the steep slopes of Keystone Canyon, one of the most challenging sections along the trans Alaska pipeline route., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-5
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

A bulldozer, modified to carry sections of 4-foot-diameter pipe, crawls up a narrow road to the top of Keystone Canyon, about 18 miles east of Valdez. The three-mile canyon is one of the more challenging engineering and construction areas along the 800-mile-long trans Alaska pipeline route., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-6
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

Four-foot diameter pipe for the trans Alaska pipeline is welded and installed on the 2,300-foot-long Yukon River bridge. The bridge, opened to pipeline construction traffic in October, 1975, was built by the State of Alaska and partially financed by Alyeska Pipeline Service Company, the firm responsible for the design, construction and operation of the pipeline., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-7
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

Sections of 48-inch diameter pipe are lowered onto a pipeway along the side of a bridge across the Yukon River. The pipe was later welded and installed in the shoe assemblies, foreground. The pipeline, being built by Alyeska Pipeline Service Company, is scheduled to begin operatin in mid-1977., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-8
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

Welders join sections of pipe for the trans Alaska pipeline in the Chugach Mountains, just north of Valdez. The pipeline is supposed to begin operation in mid-1977., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-9
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977

Welders begin one of the weld passes to join two pieces of 48-inch-diameter pipe for the trans Alaska pipeline. Six weld passes or more are made for each joint of pipe welded., 1974 - 1977

 Item — Folder: PCA0002-6
Identifier: PCA0002-6-10
Content Description From the Collection: The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates: 1974 - 1977