Although more than 150 inches of snow have fallen so far this winter, moderate temperatures have permitted outside construction activities to continue at the terminal., 1977-01
Item — Folder: PCA0002-4a
Identifier: PCA0002-4a-61
Scope and Contents
VT9058-5
Dates:
Issued: 1977-01
The ballast water treatment area at the terminal was nearing completion at year’s end. This facility will cleanse the oily ballast from incoming tankers., 1977-01
Item — Folder: PCA0002-4a
Identifier: PCA0002-4a-62
Scope and Contents
VT3054-10
Dates:
Issued: 1977-01
A chemically aided air-floatation treatment process will be used to remove virtually all hydrocarbons from the ballast water before it is returned to the port., 1977-01
Item — Folder: PCA0002-4a
Identifier: PCA0002-4a-63
Scope and Contents
VT3054-5
Dates:
Issued: 1977-01
Here, the ballast water discharge line is being installed. It will discharge cleansed water into the port about 700 to 1050 feet offshore at a depth of 200-375 feet., 1977-01
Item — Folder: PCA0002-4a
Identifier: PCA0002-4a-64
Scope and Contents
VT4029-20
Dates:
Issued: 1977-01
During the reporting period, meters were delivered to the east metering and scraper trap building., 1977-01
Item — Folder: PCA0002-4a
Identifier: PCA0002-4a-65
Scope and Contents
VT9050-6
Dates:
Issued: 1977-01
By the end of the year, the metering units were set and the piping, electrical and instrumentation tie-ins were under way., 1977-01
Item — Folder: PCA0002-4a
Identifier: PCA0002-4a-66
Scope and Contents
VT9051-2
Dates:
Issued: 1977-01
Meter delivery for the west manifold area is scheduled for February., 1977-01
Item — Folder: PCA0002-4a
Identifier: PCA0002-4a-67
Scope and Contents
VT9065-12
Dates:
Issued: 1977-01
The mechanical crude oil loading arms were installed at Berth 4, which was more than 96 per cent complete at year’s end., 1977-01
Item — Folder: PCA0002-4a
Identifier: PCA0002-4a-68
Scope and Contents
VT5113-7
Dates:
Issued: 1977-01
Loading arm bases were being set for Berth 5, which was more than 75 per cent complete., 1977-01
Item — Folder: PCA0002-4a
Identifier: PCA0002-4a-69
Scope and Contents
VT5112-12
Dates:
Issued: 1977-01
Berths 4 and 5 are required for initial operation of the pipeline in mid-1977., 1977-01
Item — Folder: PCA0002-4a
Identifier: PCA0002-4a-70
Scope and Contents
VGT5119-6
Dates:
Issued: 1977-01