Folder PCA0002-2a
Container
Contains 79 Results:
At the pump stations, material deliveries continued to improve, and by late June total progress at all the stations was more than 50%, 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-59
Scope and Contents
PS864-6
Dates:
Issued: 1976-07
Piping installation was very active at all locations. Emphasis at the stations during the summer months is on exterior work., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-60
Scope and Contents
PS866-2
Dates:
Issued: 1976-07
Cable and electrical wiring were being pulled at the stations, and conduit and major electrical equipment installation work., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-61
Scope and Contents
PS714-5
Dates:
Issued: 1976-07
Electrical work is a major portion of the work required at pump stations. About 24% of the estimated 7.4 million man hours that will be expended in pump station construction will be electrical work., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-62
Scope and Contents
PS639-2
Dates:
Issued: 1976-07
Other activities at the pump stations included hydrotesting of tanks, and installation of equipment such as motor control concerts, booster pumps and flow meters., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-63
Scope and Contents
PS865-5
Dates:
Issued: 1976-07
At the stations not required for the initial operation capacity of the pipeline, work was primarily associated with mainline corridor construction and installation of mainline pipe through the station. This is Pump Station 11., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-64
Scope and Contents
PS863-4
Dates:
Issued: 1976-07
At the Valdez terminal, good weather and improved deliveries of materials had a favorable impact on construction progress. In late June the terminal was more than half complete., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-65
Scope and Contents
VT337-12
Dates:
Issued: 1976-07
During June, a 300-foot, 400-ton boiler stack was erected at the power plant/vapor recovery facility., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-66
Scope and Contents
VT696-7
Dates:
Issued: 1976-07
Three huge cranes and about a mile of cable were needed to lift the big stack, which was shipped from California in two sections and welded together at the site., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-67
Scope and Contents
VT6107-19
Dates:
Issued: 1976-07
Months of planning and site preparation went into the tricky operation, which had to be carried out in an unusually cramped working space., 1976-07
Item — Folder: PCA0002-2a
Identifier: PCA0002-2a-68
Scope and Contents
VT6110-13
Dates:
Issued: 1976-07
