AS 17: In early March, work was progressing at a rapid pace at the pump stations, terminal and along the pipeline route., 1976-03
Item — Folder: PCA0002-1a
Identifier: PCA0002-1a-5
Scope and Contents
PC1225-11
Dates:
Issued: 1976-03
Section Map: For the pipeline portion of the project, each of the five sections was more than 50 per cent complete, with sections 1 and 4 surpassing the 60 per cent mark., 1976-03
Item — Folder: PCA0002-1a
Identifier: PCA0002-1a-6
Content Description
From the Collection:
The collection contains both slides and photographs taken during the pipeline construction. Subjects include personnel, equipment, bridge construction, the winter environment, wildlife, pump stations, Port Valdez, the Haul Road and the terminal. There are several views of archaeologists from UAF working at the site. The 589 slides generally correspond to six typewritten progress reports, which begin in March 1976, when the pipeline was about 45% complete, and end in April 1977 at 95%...
Dates:
Issued: 1976-03
Kanuti River: Much of the pipeline activity, during February, consisted of river crossings., 1976-03
Item — Folder: PCA0002-1a
Identifier: PCA0002-1a-7
Scope and Contents
PC6127
Dates:
Issued: 1976-03
Kanuti River: Here, a weighted section of pipe is being buried beneath the Kanuti River in Section 4, 1976-03
Item — Folder: PCA0002-1a
Identifier: PCA0002-1a-8
Scope and Contents
PC6127-3
Dates:
Issued: 1976-03
Chena River: In Section 3, this crossing was made for the Chena River, about four miles south of Fairbanks., 1976-03
Item — Folder: PCA0002-1a
Identifier: PCA0002-1a-9
Scope and Contents
PC6123-1
Dates:
Issued: 1976-03
Chena River: The 600- foot-long section of pipe was pulled across the river by cables., 1976-03
Item — Folder: PCA0002-1a
Identifier: PCA0002-1a-11
Scope and Contents
PC6125-18
Dates:
Issued: 1976-03
Happy Valley Area: The total project in late February was about 45 percent complete., 1976-03
Item — Folder: PCA0002-1a
Identifier: PCA0002-1a-2
Scope and Contents
PC1228-2
Dates:
Issued: 1976-03
AS 23: The Alaskan winter temperatures remained severe during February . . . ., 1976-03
Item — Folder: PCA0002-1a
Identifier: PCA0002-1a-3
Scope and Contents
PC1237-16
Dates:
Issued: 1976-03
Terminal: But the increased daylight hours spurred remobilization of the work force for all sections of the project., 1976-03
Item — Folder: PCA0002-1a
Identifier: PCA0002-1a-4
Scope and Contents
VT007-2
Dates:
Issued: 1976-03
Chena River: As for most river crossings, the pipe for the Chena crossing had been welded and concrete-coated last fall. Ditching and installation of pipe was scheduled for the winter months, when minimal disturbance would be caused to the fish habitat and-to the rivershed itself., 1976-03
Item — Folder: PCA0002-1a
Identifier: PCA0002-1a-10
Scope and Contents
PC6129-3
Dates:
Issued: 1976-03